chart board date question  XML
Forum Index -> Support
Author Message
msumrell


Joined: 03/10/2007 13:23:51
Messages: 58
Offline

Our chart board has an end date of 10/31 (today). A few tasks were updated this morning. However, it looks like it won't take the data from today on the chart board. The time remaining on the planning board is 22 hours but the chart board is still showing 29 hoours (which was where it was at the end of the day yesterday). If I change the end date to tomorrow, then the chart board data is correct but it looks like we have one more day in the sprint. Does the chart board not take data entered on the last day?
jchuet

[Avatar]

Joined: 13/09/2006 09:08:24
Messages: 1000
Offline

Hi M,

Yep we fell on the same behavior on our own charts.
The release date registered in JIRA and the one you override in the charts is the begin of the day.
i.e. 31/11/2007 00:00:00

We have changed it to be the end of the day
i.e. 31/11/2007 23:59:59

so that your logs done on the release date are computed.

Its part of the fix in release 1.5
[Email]
msumrell


Joined: 03/10/2007 13:23:51
Messages: 58
Offline

great!! thank you!
 